The development and construction of berth No.11 and 11A at Umm Qasr port
Constructing more than 100,000 m2 of stacking yards utilizing for the first time in Umm Qasr port the use of interlock paving stone as bearing floor
Development / Construction
Client
Prime Metro Power Holdings Corporation (PMPH)
Start Date
27/04/2019
Contract
EPC
Duration
6 Months
Basrah Mas was contracted by Prime power on behalf of GCPI to design and construct a 10″ main gas pipeline feeder of 15 km length to feed Umm Qasr gas fired power plant.
Feeding capacity 25 mmscf/day along with all in plant feeding connections. All field inspection is carried out by Oil Pipeline Company (Government company). A major crossing of 150 m.l is foreseen in this project conducted by HDD technique.
Constructing more than 100,000 m2 of stacking yards utilizing for the first time in Umm Qasr port the use of interlock paving stone as bearing floor
Construction of interlock paved 150,000 m2 area for containers stacking.
An area for containers handling and storage with a total area of 100,000 m2 with multi-functional covered storages and ancillary buildings.