Development / Construction

Dredging work in front of berth No.27

Client

ICTSI/ BGT

Start Date

11/05/2017

Contract

Unit price

Duration

6 Months

A total of 800,000 cubic meters of materials were dredged in front of berth 27 to reach to navigational depths in accordance with requirement of Umm Qasr port navigational depths. IHC suction cutter dredgers were used with a maximum dredging depth of 16 meters and in/out suction pipe of 600mm

See Also

Berth No.27 at Basrah Gateway Terminal (BGT)

Basrah Mas was selected as a sole main contractor to International Container Terminal Services Inc. (ICTSI) to construct
three berths at their Basrah Gateway Terminal (BGT) in Umm
Qasr Port.