Development / Construction

The development and construction of berth No.11 and 11A at Umm Qasr port

Client

General Company for Ports of Iraq (GCPI)

Start Date

01/05/2009

Contract

EPC

Duration

15 Months

The work constituted of constructing the quay structure and all ancillaries, as well as constructing more than 100,000 m2 of stacking yards utilizing for the first time in Umm Qasr port the use of interlock paving stone as bearing floor

See Also

Control tower at Umm Qasr port